O2C Reconciliation Modernization
L6 — UAT & Closure
Did It Actually Do What L0–L5 Claimed?
Every earlier layer labeled its numbers Actual or Assumption. L6 is the check on that discipline itself — re-verifying the claims against what's actually embedded in the L2–L4 code and output, logging what didn't work the first time, and closing the project against the criteria set back in L0–L2.
Source: L2/L4 code comments + KPI labels, re-checked directly Scope: 6 test cases + 1 defect — limited to what's verifiable, not padded Built: Aug 2026
This is not a full regression suite. It's an honest re-verification of the specific claims L0–L5 made, using only evidence that exists in the built artifacts — six test cases and one defect, not an inflated list.
Contents
01
UAT approach
Who tested this, and why that has to be stated plainly
This is a self-directed case study — there's no separate business stakeholder to hand this off to for acceptance testing. Every test below was designed and run by the same person who built L0–L5, wearing both the "builder" and "acceptance reviewer" hat. That's a real limitation on independence, and it's stated here directly rather than implied away by formal-sounding UAT language.
To keep that limitation from becoming an excuse for weak testing, the test cases below are restricted to claims that can be checked two ways: against a code comment or label already embedded in L2–L4 at build time, and against a fresh recalculation done while writing this page. A test only counts as run if both checks agree.
What this UAT is not
Not a full regression suite, not independent QA, not a claim that every corner of L0–L5 was tested. It's a re-verification of the specific numeric and behavioral claims those layers made, using evidence that already exists in the code and output — nothing was tested that isn't traceable to something built.
02
Test case matrix
Re-checking L4's numeric and behavioral claims against the code and KPI labels that produced them
Each row below traces to a specific line in L2/L4: a SQL comment, a KPI card label, or an AI-package field. "Expected" is what that layer claimed; "actual" is what re-checking the artifact directly shows.
idtestexpectedactualresult
TC-01Row-count reconciliation, L4 vs. L2/L31,618 total · 622/614/255/83/30/14 by typeMatches — per verification comment in l4_risk_assessment queryPASS
TC-02Business-category rollup sums to total4 categories sum to 1,618735 + 614 + 255 + 14 = 1,618PASS
TC-03Financial exposure reconciliationR$271,891.01 totalMatches L4's "Actual — verified vs. L2/L3" KPI cardPASS
TC-04Metric-name disambiguationL4's 98.37% must not be confused with L2's 98.85%KPI sub-label explicitly states "distinct from L2's 98.85% amount-match rate"PASS
TC-05NULL order_total not silently treated as confirmed valueAI package must flag the gap, not substitute payment_total2 affected orders — recommended_action explicitly says "do not rely on payment_total alone as confirmation"PASS
TC-06Zero-exposure tie-break determinism (14 APPROVAL_GAP orders, all R$0)Tier assigned by purchase-date order, not fabricated dollar variancePackage text for all 14 explicitly attributes tier to the purchase-date tie-breakPASS
6 of 6 pass. Every failure mode a portfolio reviewer would probe first — do the totals actually add up, does a similar-looking percentage get conflated with a different one, does a missing field get glossed over — was checked directly against the artifact, not asserted.
03
Defect log
One real defect, found and fixed during L2 — not a padded list
idfound inseveritydescriptionfix
DEF-01L2 — exception classificationMEDCASE WHEN branch order placed amount-based flags before business-status flags; since CASE WHEN resolves at the first true condition, canceled-with-payment orders were being misclassified before the cancellation check ever ranReordered branches so business-status flags evaluate first; financial exposure for canceled orders recomputed with SUM(payment_total) directly instead of the reconciliation-difference column
Why this is the only entry
This defect was caught during L2's own build and fixed before L2 was marked done — it's included here rather than hidden because a defect log with one honest, real entry is more credible than one with several invented to look thorough.
04
Acceptance criteria & sign-off
Checked against the targets L0–L2 set at the start, not criteria written after the fact
criteriontargetactualresult
Reconciliation match rate≥95% (set in L2)98.85% amount-match rateMET
Row-count integrity L2→L3→L4Exact match, no drift1,618 confirmed at every layer (TC-01, TC-02)MET
No AI write-back to system of recordZero write-back code paths (L4 design constraint)Validation buttons log a decision string only; no ledger-write path existsMET
Every financial claim traceable to L2/L3 sourceNo unlabeled or invented figures in L0–L5All Actual-labeled figures re-checked in Step 02 aboveMET
Signed off byArthunya Kanoklertwongse (self-certification — sole contributor, see Step 01)
Scope certifiedL0–L6, O2C Reconciliation Modernization
Basis6/6 test cases pass, 1 defect logged and resolved, 4/4 acceptance criteria met
DateAug 2026
05
Project closure & retrospective
Where this landed against the original Gate 1 target, and what each layer was actually for
The original Gate 1 target was L0–L2 complete plus a first wave of job applications sent by 31 August 2026. All seven layers — L0 through L6 — are complete ahead of that date, which is worth stating plainly without overselling it: the extra layers exist because the case study kept surfacing real BA/BSA-relevant questions (governance, ROI honesty, acceptance testing) worth answering, not because the original scope required it.
layerwhat it actually proved
L0Understanding the business problem before touching a tool
L1Designing a process on paper before writing a query
L2Turning business rules into verified SQL — and catching a real branch-order bug along the way
L3Communicating findings through a dashboard, and treating a tooling pivot (static HTML over Power BI publish) as a deliberate choice, not a failure
L4Deciding where AI belongs in a workflow, and designing a system where it structurally can't overstep that boundary
L5Separating what's measured from what's assumed in a business case, instead of blending them into one impressive number
L6Applying that same honesty to testing itself — six real checks beat thirty invented ones
Closed. This case study set out to show how a Business Analyst redesigns a financial review process end-to-end — discovery through UAT — on public data, with every claim either verified or explicitly labeled as an assumption. L6 is the layer that checks whether that discipline actually held up, and it did.
★
Lesson: The same instinct that made L5's R$199.52 more credible than R$271,891.01 applies to testing — a short, honest test matrix that's actually traceable to the code beats a long one that isn't. In an interview, "here are the six things I checked and how" holds up to follow-up questions in a way a padded list doesn't.